Drywall Prep: Install the nailers for drywall.

These are all finished now. Unless the drywallers find they need another one somewhere.

Hallway Nailers

Hallway Nailers

There are some tricky areas where the house orientation changes direction to catch the sun. The rafters come together at an angle and the nailers had to follow that angle and remain about 24″ apart to screw in the drywall.

Room Angle Change

Room Angle Change

In the master bedroom the house again changes orientation this time to the west. So the rafters are also at an angle and the nailers had to make up this difference.

Another tricky area

Another tricky area

In the front hall and family room closets, the temporary membrane holding board was just left there in the middle and the two nailers installed on either side.

Leaving the temporary board

Leaving the temporary board

There may be a nailer or two to finish in the utility room but essentially this step is completed.

This entry was posted in Air Intrusion/Thermal Envelope. Bookmark the permalink.