Drywall Prep: Ensure Denshield in Bathrooms

I signed the drywall contract and the work is to begin April 24th. Included in the contract is Denshield in the bathrooms. We decided to have the walls match the existing knockdown texture but have the ceilings be smooth which … Continue reading

Posted in Construction, LEED Project | Comments Off on Drywall Prep: Ensure Denshield in Bathrooms

Drywall Prep: Install the nailers for drywall.

These are all finished now. Unless the drywallers find they need another one somewhere. There are some tricky areas where the house orientation changes direction to catch the sun. The rafters come together at an angle and the nailers had … Continue reading